# Report, sprint five
|
|
|
|
|
|
|
|
# Status
|
|
|
|
|
|
|
|
- Updated: 25.7.2018
|
|
|
|
|
|
|
|
- Team: IoTitude
|
|
|
|
|
|
|
|
## Sprint goals
|
|
|
|
|
|
|
|
- Manual for each component of the system
|
|
|
|
|
|
|
|
- Documentation for each component of the system
|
|
|
|
|
|
|
|
- Complete tests for each component in the system
|
|
|
|
|
|
|
|
## Progress
|
|
|
|
|
|
|
|
Every manual except Gitlab CI is done and most of them have been tested. Documentation is on it's way if not done already. Some manual tests were done by us internally, but due to time scares we outsourced manual tests for Mysticons, hopefully they will be able to give us some feedback on the manuals aswell.
|
|
|
|
|
|
|
|
Mob programming used couple days at the beginning of the sprint to refactor game code, after which the code works fine but websocket (RuuviTag - Monogame communication) seems to have been borged.
|
|
|
|
|
|
|
|
## What everyone is doing
|
|
|
|
|
|
|
|
### Headless Horsechicken (Rami)
|
|
|
|
|
|
|
|
Writing report for the whole project and trying hard to stay focused. END IS NEAR!
|
|
|
|
|
|
|
|
### Test and analytics (Joona)
|
|
|
|
|
|
|
|
Gitlab CI chain is about done now, and manual should be ready at the end of this sprint.
|
|
|
|
|
|
|
|
### Gameguys (Konsta, Santeri)
|
|
|
|
|
|
|
|
Mob programming monogame code refactoring and combining existing solutions to one solution for master branch
|
|
|
|
|
|
|
|
Manual testing and code fixes
|
|
|
|
|
|
|
|
### gRPC group / Second gamesquad (Kasper, Carita)
|
|
|
|
|
|
|
|
Part of the mob and then unit tests for gRPC using Jest, Carita has been helping Rami writing reports (Proof reading).
|
|
|
|
|
|
|
|
### Ruuvi dudes (Aku, Mika)
|
|
|
|
|
|
|
|
Aku has been doing Test cases and Mika has been communicating with overflow and writing unit tests for python.
|
|
|
|
|
|
|
|
### User orientation (Pinja (+ muu hyvin tiimi))
|
|
|
|
|
|
|
|
Link has been cut.
|
|
|
|
|
|
|
|
## Ticket situation
|
|
|
|
|
|
|
|
some tickets have been closed due to there being no time to develop them and the motif of the sprint doesn't allow any new development.
|
|
|
|
|
|
|
|
Backlog is clear and we have 8 open tickets.
|
|
|
|
|
|
|
|
## Can we finish everything
|
|
|
|
|
|
|
|
Absolutely maybe!
|
|
|
|
|
|
|