Milestones
Open
11
Closed
0
All
11
Due soon
sprint 00 - G0
ZZPP0920 / en-2025
Jan 13, 2025–Jan 17, 2025
Expired
10/10 complete
100%
sprint 01
ZZPP0920 / en-2025
Jan 20, 2025–Jan 31, 2025
Expired
30/30 complete
100%
sprint 02
ZZPP0920 / en-2025
Feb 3, 2025–Feb 14, 2025
Expired
13/13 complete
100%
sprint 03 - G1
ZZPP0920 / en-2025
Feb 17, 2025–Feb 28, 2025
Expired
11/11 complete
100%
sprint 04
ZZPP0920 / en-2025
Mar 3, 2025–Mar 14, 2025
Expired
9/9 complete
100%
sprint 05 - G2
ZZPP0920 / en-2025
Mar 17, 2025–Mar 28, 2025
Expired
10/10 complete
100%
sprint 06
ZZPP0920 / en-2025
Mar 31, 2025–Apr 11, 2025
Expired
8/8 complete
100%
sprint 07 -G3 + G4
ZZPP0920 / en-2025
Apr 14, 2025–Apr 25, 2025
Expired
0/8 complete
0%
sprint 08
ZZPP0920 / en-2025
Apr 28, 2025–May 2, 2025
Expired
0/0 complete
0%
postponed
ZZPP0920 / en-2025
started on May 1, 2025
Open
60/62 complete
96%
backlog
ZZPP0920 / en-2025
started on Jan 13, 2025
Open
0/0 complete
0%