# Template of Project Offer
Example of offer
# Recipient of the offer: xxxxx, Company Ltd.
Referring to your request for offer request x.y.zzzz, we offer you the following service product:
## 1. Object of the tender and procurement situation
The "XXXX" solution / service to be implemented in this case means an entity comprising the following functionalities:
__For example__
* Feature [Feature 10](../../20-Requirement-management/templates/template-feature.md) as well as giving feedback [Feature 13](../../20-Requirement-management/templates/template-feature.md)
* the institution can add courses [Feature 5](../../20-Requirement-management/templates/template-feature.md), manage accounts [Feature 12](../../20-Requirement-management/templates/template-feature.md) and collect data from the above options [Feature 15](../../20-Requirement-management/templates/template-feature.md) + [Feature 18](../../20-Requirement-management/templates/template-feature.md)
* students can make course choices from courses set by the institution [Feature 2](../../20-Requirement-management/templates/template-feature.md)
**A more detailed description can be found in [requirements specification](../../20-Requirement-management/wide-requirement-specification.md)**
## 2. Objectives, requirements and proposed solutions
Preliminary MockUp concept (Appendix 1)
## 3. Delivery and release plan
⦁ Phasing and timetable (Annex 2)
### Steps:
* [E1]() Signing of the project agreement on 12.10.202x
* [E2]() Final testing plan made on 7 November 202x
* [E3]() Trial operation 21.11.202x
* [E4]() Commissioning on 12.12.202x
* Preliminary test plan (Appendix 3)
* Agile Scrumban model as a system work method
## 4. Prices and charges
Total price € 81,000.00 (incl. VAT 24%), according to the following schedule
* payment point € due date *
* E1 Signing of the Agreement 26,000.00 on October 19, 2018
* E2 Final testing plan 15,000.00 14.11.2018
* E3 Approval testing 20,000.00 on November 28, 2018
* E4 Commissioning 20,000.00 on 19.12.2018
* Payment due date 7 days from the stage
**Division of labor:**
* Control + administration A%
* definition and design B%
* coding and testing C%
* documentation D%
## 5. Supplier Introduction
* Project group XXZZ: www.sivut.fi
* for more information, contact abc.def@gg.fi
## 6. Other things to consider
* Limitations of the “hair coat model” offered:
* in Finnish
* limited to JAMK's ICT student courses
* user numbers limited to JAMK's ICT students
* contacts are requested primarily by Slack messages, secondarily by email
* the offer is valid until 12.10.2018
Signatures
x.x.xxxx
XYZ
project manage